Generator overhaul: what is done in 9 steps

Generator overhaul in 9 steps: rotor removal, stator, insulation, EL CID, rotor test, retaining rings, wedges and final tests.

Published · 68.5 seconds · subtítulos en español

Email ventas@temisapowergen.mxWhatsApp

Short answer

What is done to a generator in an overhaul?

A generator overhaul is nine steps in the same order: the outage is planned, the rotor is uncoupled and removed, the stator is inspected, insulation tests are run with a polarization index of at least two, and the EL CID test looks for shorts between laminations. The most important step is the rotor test: a shorted turn causes vibration and no stator test finds it. Then come retaining rings, cleaning, wedges, varnish, assembly and final tests.

Video transcript

Download captions (.srt)
  1. 00:00

    What is done to

  2. 00:01

    a generator in an

  3. 00:01

    overhaul?

  4. 00:03

    9 steps,

  5. 00:03

    always in the same

  6. 00:04

    order.

  7. 00:05

    And the most important

  8. 00:06

    one can't be seen

  9. 00:07

    with the naked eye.

  10. 00:08

    1. You call TEMISA Power

  11. 00:10

    Gen and we plan

  12. 00:11

    the outage with you.

  13. 00:13

    2. It is uncoupled and

  14. 00:14

    the rotor is removed.

  15. 00:16

    3. The stator is inspected:

  16. 00:18

    wedges, end windings and

  17. 00:20

    contamination.

  18. 00:21

    4. Insulation tests.

  19. 00:23

    The polarization index must

  20. 00:25

    be at least two.

  21. 00:26

    5. The EL CID test

  22. 00:29

    looks for shorts between

  23. 00:30

    core laminations.

  24. 00:31

    6. The most important:

  25. 00:33

    the rotor test.

  26. 00:35

    A shorted turn causes

  27. 00:36

    vibration, and no stator

  28. 00:37

    test will detect it.

  29. 00:39

    7. The retaining rings are

  30. 00:40

    inspected.

  31. 00:42

    8. Cleaning, wedge tightening and

  32. 00:44

    varnish.

  33. 00:45

    9. It is assembled,

  34. 00:46

    the air gap is

  35. 00:47

    checked and final tests

  36. 00:48

    are done.

  37. 00:49

    It's not what you

  38. 00:50

    see, it's what you

  39. 00:51

    measure.

  40. 00:52

    Comment OVERHAUL and we'll

  41. 00:53

    tell you what to

  42. 00:54

    check on your generator.

  43. 00:55

    TEMISA Power Gen: over 70 years in generators and electrical machines, ISO 9001:2015 and CFE LAPEM certificate. Contact: ventas@temisapowergen.mx.

Questions from plant owners

What is the most important step in a generator overhaul?

The rotor test. A shorted turn causes vibration and no stator test detects it.

What polarization index should the insulation give?

At least two, as the IEEE 43 reference for most insulation systems.

What is the EL CID test for?

It looks for shorts between the stator core laminations before reassembly.

Does TEMISA Power Gen overhaul generators?

Yes, on site or at the Tlajomulco shop depending on the outage. To quote, send the nameplate and outage window to ventas@temisapowergen.mx.

About the figures: Figures and graphics in the video illustrate the procedure. They are not a measurement from a serviced generator and they are not acceptance limits.

About the footage: Inserted photos are from the TEMISA Power Gen shop in Tlajomulco, Jalisco; the explanation is an animation and shows no customer data.

Narration of the TEMISA Power Gen explainer video.