TEMISA Power Gen · Explainer
Ver en españolGenerator overhaul: what is done in 9 steps
Generator overhaul in 9 steps: rotor removal, stator, insulation, EL CID, rotor test, retaining rings, wedges and final tests.
Published · 68.5 seconds · subtítulos en español
Short answer
What is done to a generator in an overhaul?
A generator overhaul is nine steps in the same order: the outage is planned, the rotor is uncoupled and removed, the stator is inspected, insulation tests are run with a polarization index of at least two, and the EL CID test looks for shorts between laminations. The most important step is the rotor test: a shorted turn causes vibration and no stator test finds it. Then come retaining rings, cleaning, wedges, varnish, assembly and final tests.
Video transcript
Download captions (.srt)- 00:00
What is done to
- 00:01
a generator in an
- 00:01
overhaul?
- 00:03
9 steps,
- 00:03
always in the same
- 00:04
order.
- 00:05
And the most important
- 00:06
one can't be seen
- 00:07
with the naked eye.
- 00:08
1. You call TEMISA Power
- 00:10
Gen and we plan
- 00:11
the outage with you.
- 00:13
2. It is uncoupled and
- 00:14
the rotor is removed.
- 00:16
3. The stator is inspected:
- 00:18
wedges, end windings and
- 00:20
contamination.
- 00:21
4. Insulation tests.
- 00:23
The polarization index must
- 00:25
be at least two.
- 00:26
5. The EL CID test
- 00:29
looks for shorts between
- 00:30
core laminations.
- 00:31
6. The most important:
- 00:33
the rotor test.
- 00:35
A shorted turn causes
- 00:36
vibration, and no stator
- 00:37
test will detect it.
- 00:39
7. The retaining rings are
- 00:40
inspected.
- 00:42
8. Cleaning, wedge tightening and
- 00:44
varnish.
- 00:45
9. It is assembled,
- 00:46
the air gap is
- 00:47
checked and final tests
- 00:48
are done.
- 00:49
It's not what you
- 00:50
see, it's what you
- 00:51
measure.
- 00:52
Comment OVERHAUL and we'll
- 00:53
tell you what to
- 00:54
check on your generator.
- 00:55
TEMISA Power Gen: over 70 years in generators and electrical machines, ISO 9001:2015 and CFE LAPEM certificate. Contact: ventas@temisapowergen.mx.
Questions from plant owners
What is the most important step in a generator overhaul?
The rotor test. A shorted turn causes vibration and no stator test detects it.
What polarization index should the insulation give?
At least two, as the IEEE 43 reference for most insulation systems.
What is the EL CID test for?
It looks for shorts between the stator core laminations before reassembly.
Does TEMISA Power Gen overhaul generators?
Yes, on site or at the Tlajomulco shop depending on the outage. To quote, send the nameplate and outage window to ventas@temisapowergen.mx.
About the figures: Figures and graphics in the video illustrate the procedure. They are not a measurement from a serviced generator and they are not acceptance limits.
About the footage: Inserted photos are from the TEMISA Power Gen shop in Tlajomulco, Jalisco; the explanation is an animation and shows no customer data.
Narration of the TEMISA Power Gen explainer video.